A constraint in the model means:__________.
1. activity A should be finished within 2 weeks.
2. the total time taken by activity A cannot be more than 2 weeks.
3. activity A cannot be crashed by more than 2 weeks.
4. activity A must be finished in week 2 after the start of the activity.
5. none of the above.

Respuesta :

Answer:

The correct answer to the given question will be Option C.

Explanation:

The YA has been used to describe or portray the period that intervention A crashes for.

The total number of weeks A may malfunction would have been:

⇒  [tex]normal \ times-crash \ time[/tex]

⇒  [tex]5-3[/tex]

⇒  [tex]2 \ weeks[/tex]

then,

⇒  [tex]Y_{A} <=2 \ means[/tex]

The other given choices are not related to the given situation. So that option C would be the appropriate choice.