An all-equity firm is considering the following projects:
Project Beta IRR
W .62 9.2 %
X .77 10.3
Y 1.27 14.1
Z 1.42 17.0
The T-bill rate is 5 percent, and the expected return on the market is 12 percent.
A. Compared with the firm's 12 percent cost of capital, Project W has a_______expected return.
a. lower
b. higher
1. Project X has a______expected return.
a. higher
b. lower
2. Project Y has a_______expected return
a. lower
b. higher
3. Project Z has a______expected return.
a. higher
b. lower
B. Project W should be_______.
a. accepted
b. rejected
1. Project X should be______.
a. accepted
b. rejected
2. Project Y should be_______.
a. accepted
b. rejected
3. Project Z should be_______.
a. accepted
b. rejected
c. If the firm's overall cost of capital were used as a hurdle rate, Project W would be_______.
a. correctly accepted
b. incorrectly rejected
c. correctly rejected
d. incorrectly accepted
1. Project X would be______.
a. correctly accepted
b. incorrectly accepted
c. correctly rejected
d. incorrectly rejected
2. Project Y would be_______.
a. correctly rejectedin
b. correctly accepted
c. incorrectly rejected
d. correctly accepted
3. Project Z would be________.
a. incorrectly accepted
b. correctly rejected
c. incorrectly rejected
d. correctly accepted.

Respuesta :

Answer:

A. Compared with the firm's 12 percent cost of capital, Project W has a_______expected return.

  • a. lower

1. Project X has a______expected return.

  • b. lower

2. Project Y has a_______expected return

  • b. higher

3. Project Z has a______expected return.

  • a. higher

B. Project W should be_______.

  • b. rejected

1. Project X should be______.

  • b. rejected

2. Project Y should be_______.

  • a. accepted

3. Project Z should be_______.

  • a. accepted

c. If the firm's overall cost of capital were used as a hurdle rate, Project W would be_______.

  • c. correctly rejected

1. Project X would be______.

  • c. correctly rejected

2. Project Y would be_______.

  • b. correctly accepted

3. Project Z would be________.

  • b. correctly rejected

Explanation:

Project    Beta     IRR         expected return

W             .62      9.2%       = 5% + (0.62 x 7%) = 9.34%

X              .77      10.3 %     = 5% + (0.77 x 7%) = 10.39%

Y            1.27       14.1 %      = 5% + (1.27 x 7%) = 13.89%

Z            1.42       17.0%     = 5% + (1.42 x 7%) = 14.94%

ACCESS MORE
EDU ACCESS