Drum buffers are:_________
A. Extra safety that is applied to a project immediately before the use of the constrained resource.
B. A constraint separating different projects that requires a common buffer.
C. A safety margin separating different projects scheduled to use the same resource.
D. Extra safety that is applied to a project immediately after the use of the constrained resource.