Respuesta :
Answer:
Kindly see explanation
Explanation:
Given the following:
Initial investment = $8,000,000
Future value (FV) = $10,000,000
PERIOD (t) = 5 Years
To know if the form should undertake the project, the present value(PV) at each interest rate should be calculated ;
A.) Interest rate (r) = 7% = 0.07
PV = FV / (1 + r)^t
PV = 10,000,000 / (1 + 0.07)^5
PV = 10,000,000 / 1.07^5
PV = 10,000,000 / 1.4025517307
PV = $7,129,861.79483668
Should not be undertaken, PV is less than initial investment.
B.) Interest rate (r) = 6% = 0.06
PV = FV / (1 + r)^t
PV = 10,000,000 / (1 + 0.06)^5
PV = 10,000,000 / 1.06^5
PV = 10,000,000 / 1.3382255776
PV = $7,472,581.72866057
Should not be undertaken, PV is less than initial investment.
C.) Interest rate (r) = 5% = 0.05
PV = FV / (1 + r)^t
PV = 10,000,000 / (1 + 0.05)^5
PV = 10,000,000 / 1.05^5
PV = 10,000,000 / 1.2762815625
PV = $7,835,261.66468459
Should not be undertaken, PV is less than initial investment
D.)Interest rate (r) = 4% = 0.04
PV = FV / (1 + r)^t
PV = 10,000,000 / (1 + 0.04)^5
PV = 10,000,000 / 1.04^5
PV = 10,000,000 / 1.2166529024
PV = $8,219,271.06759351
Should be undertaken, PV is greater than initial investment
The firm should undertake the project for each of the interest rates listed for Undertake Project :
A) 7% is No.
B) 6% is No.
C) 5% is No.
D) 4% is Yes.
Undertake Project
Given:
Initial investment = $8,000,000
Future value (FV) = $10,000,000
PERIOD (t) = 5 Years
Part A:
Initial investment = $8,000,000
Future value (FV) = $10,000,000
Time (t) = 5 Years
Interest rate (r) = 7% = 0.07
Present Value =PV[tex]PV = FV / (1 + r)^t[/tex]
PV =[tex]10,000,000 / (1 + 0.07)^5PV = 10,000,000 / 1.07^5[/tex]
PV = [tex]10,000,000 / 1.4025517307[/tex]
PV = [tex]$7,129,861.79483668.[/tex]
Thus, the project should not be undertaken as the present value is less than initial investment.
Part B:
Initial investment = $8,000,000
Future value (FV) = $10,000,000
Time (t) = 5 Years
Present Value =PV
Interest rate (r) = 6% = 0.06[tex]
PV = FV / (1 + r)^t[/tex]
PV = [tex]10,000,000 / (1 + 0.06)^5[/tex]
PV =[tex]10,000,000 / 1.06^5[/tex]
PV = [tex]10,000,000 / 1.3382255776[/tex]
PV = [tex]$7,472,581.72866057[/tex]
Thus, the project should not be undertaken as the Present value is less than initial investment.
Part C:
Initial investment = $8,000,000
Future value (FV) = $10,000,000
Time (t) = 5 Years
Present Value =PV
Interest rate (r) = 5% = 0.05[tex]
PV = FV / (1 + r)^t[/tex]
PV =[tex]10,000,000 / (1 + 0.05)^5[/tex]
PV =[tex]10,000,000 / 1.05^5[/tex]
PV = [tex]$7,835,261.66468459[/tex]
Thus, the project should not be undertaken as the Present value is less than initial investment.
Part D:
Initial investment = $8,000,000
Future value (FV) = $10,000,000
Time (t) = 5 Years
Present Value =PV
Interest rate (r) = 4% = 0.04
PV = FV / (1 + r)^t[/tex]
PV = [tex]10,000,000 / (1 + 0.04)^5[/tex]
PV = [tex]10,000,000 / 1.04^5[/tex]
PV = [tex]10,000,000 / 1.2166529024[/tex]
PV = [tex]$8,219,271.06759351[/tex]
Thus, the project should be undertaken as the Present Value is greater than initial investment.
Thus, the correct option is D.
Learn more about "Present Value":
https://brainly.com/question/12984968?referrer=searchResults