Answer:
Purchases= $26,550
Explanation:
Giving the following information:
Production:
January= 2,900 units
February= 3,600 units
Norton budgets $20 per unit for direct materials.
Beginning inventory raw materials= $38,650.
Desired ending inventory direct materials= 10% of the next month's direct materials needed for production.
To calculate the purchases of direct material, we need to use the following formula:
Purchases= production + desired ending inventory - beginning inventory
Purchases= 2,900*20 + (3,600*0.1)*20 - 38,650
Purchases= $26,550