Answer:
The answer to the question is False.
Explanation:
Materials Price and Efficiency Variance measures cost of materials purchased against the amount budgeted for it. When materials which are higher in quality are purchased at a lower price, the Materials Price Variance is said to be favorable. This means that it should lead to a lower number of rejected units given that one purchased materials of higher quality.
Labor price variance is favourable if the actual cost of labor to the organisation fall below the budgeted amount.
The measure of expected output from a certain input of materials is referred to as material yield variance. Material yield variance is directly related to labour efficience variance.
A favorable labor price/material yield variance should result in faster work pace and lower of waste or rejects.
Therefore the above assertions are false.
Cheers!