55 men can finish a piece of work in 42 days. How many additional men must be added to complete the work 9 days earlier.​

Respuesta :

[tex]55 . 42 = x . 33\\55 . 14 = 11 . x\\x = 5 . 14 = 70\\70 - 55 = 15[/tex]Answer:

Step-by-step explanation:

The additional men required to complete this work 9 days earlier will be 15.

What is work time?

In time and work, we need to calculate the time required to complete a unit of work and find work done in a described period of time. Its known the amount of work done by a person varies directly with the time taken by them to complete the work on time.

Given that work was done by 55 men in 42 days

55 men ⇔ 42 days

Rate of work by 1 man ⇔ 1/(55×42)

Rate of work by 1 man ⇔ 1/(2310)

Now by adding N number of people the work need to complete 9 days earlier than 33 days.

Rate of work by 1 man ⇔ 1/[(55+N)×33]

Since the rate of work by 1 man will be the same for both cases

1/(2310) = 1/[(55+N)×33]

N = 15 hence,15 men additional required to complete the work 9 days earlier.

For more information about work time

https://brainly.com/question/19382734