Respuesta :
Answer:
Budgeted overhead cost =$1,250,000
Explanation:
Budgeted overhead for the month of September = Total labour hours × overhead rate per hour
Total labor hours = standard hours × budgeted production units
=2.5 hours × 40,000= 125,000
Budgeted overhead cost Total = $10× 125,000 =$1250000
Budgeted overhead cost =$1,250,000
Answer:
$1,254,500
Explanation:
Solution
Recall that:
Production of sneakers for three months budgets were :
August= 28000
September = 50,000
October = 33,000
Each sneakers requires labor time = 2.5 hours
Labor wages average = $16.
Now,
The total overhead budgeted for the month of September is calculated as follows:
The total overhead budgeted for the month of September = Variable overhead + Fixed overhead
= (50,000 units * 2.5 direct labor hours per unit * $10 per direct labor hour) + $4,500
= $1,254,500
Therefore, the total overhead budgeted for the month of September is $1,254,500
