Answer:
Explanation:
Bid price - $450,000
Contract cost 2016- $ 180,000
Contract cost in 2017 - $195,000
Gross profit = $75,000
Estimated cost to complete at 2016 - $200,000
Percentage completion in 2016 - 180000/380000* 100 =47 %
Revenue recognized in 2016 - 47% * 450,000 = 211,500
Gross profit = 211,500- 180,000 = 31,500
2017
Revenue recognized - 53% = $238,500
Cost $195,000
Gross profit $43,500
3)Completed contract method -
Income are recognized when contract is completed
2016 - No revenue generated / recorded
2017
Revenue - 450,000
Cost to date - 375,000
Gross profit - 75,000
4) When using the cost recovery method under IFRS , an equal amount of income and revenue is recognized in the early life time of the project
2016
Income - 180000
Cost- 180000
Gross profit - 0
2017
Income -450000
cost 375,000
Gross profit - $75,000