Answer:
Therefore 13.3 ideas per week
Explanation:
We can use the following method to do the calculations
And we are given
The average number of ideas per week =25
Ideas approved per week = 25×0.6×0.5×0.35×0.75
= 1.968 ideas
b)
The maximum time that will be taking stage is Testing therefore it is the bottleneck base on current staffing plan.
c)
Capacity per hour = number of staff ÷ number of hour
We have capacity per week = Capacity per hour ×5× 8
Demand is lowest of all capacity
= 13.3
Paper screening
Capacity= 3/2=1.5 idea/ hour
= 60 idea per week
Demand =13.3
Utilization=0.22
Design & production
Capacity= 4/4=1 idea/ hour
= 40 idea per week
Demand =13.3
Utilization=0.33
Testing
Capacity= 6/16=0.38 idea/ hour
= 15 idea per week
Demand =13.3
Utilization=0.88
Focus group
Capacity= 1/2=0.5 idea/ hour
= 20 idea per week
Demand =20
Utilization=0.66
Final decision
Capacity= 1/3=0.33 idea/ hour
= 13.3 idea per week
Demand =13.3
Utilization=1
Thus 13.3 ideas per week as our answer