Answer:
Net present value of the project is closest to $15,542.00
Explanation:
The net present value of the project is the present value of cash inflows minus the initial investment.
The present value of the cash inflows is the yearly cash inflow of $133,000 multiplied by the annuity of 13% for 4 years i.e 2.974
Present value of inflows=2.974*$133,000=$ 395,542.00
initial investment is $380,000
Net present value=$ 395,542.00-$380,000.00=$15,542.00