Teel Printing uses two measures of activity, press runs, and book set-ups, in the cost formulas in its budgets and performance reports. The cost formula for wages and salaries is $7,850 per month plus $402 per press run plus $952 per book set-up. The company expected its activity in July to be 206 press runs and 113 book set-ups, but the actual activity was 203 press runs and 112 book set-ups. The actual cost for wages and salaries in July was $196,180.
The spending variance for wages and salaries in July would be closest to

Respuesta :

Answer:

Spending variance                              $100 unfavorable

Explanation:

The spending variance is the difference between the standard cost allowed for the actual activity and the actual cost of the activity

                                                                                                    $

Standard cost allowed for the actual activity

=7,850 + (402×203) + (952×112)=                                          196,080

Actual cost                                                                                196,180

Spending variance                                                                       100 unfavorable