Option C is correct - allocate all of its production capacity to Product Y.
Explanation:
1. Contribution margin per production hour
Product X Product Y
Contribution margin per unit $8 $7
Units produced per hour 2 3
Contribution margin per production hour $16($8*2) $21($7*3)
2. The most profitable sales mix for this company is to allocate all of its production capacity to Product Y.
Option C is correct.