Respuesta :
Answer:
The required cycle time for this assembly line is 2 minutes. The rigtht answer is c.
Explanation:
Acording to the data, we have the following:
Daily operating time= factory operates 1000 minutes per day
Scheduled output=make 500 El-More dolls per day
Therefore, to calculate the required cycle time for this assembly line we have to use the following formula:
Cycle time = daily operating time divided by the scheduled output
= 1000 / 500 = 2 minutes
The required cycle time for this assembly line is 2 minutes.
Answer:
The required cycle time for this assembly line is 2 minutes.
Explanation: Given that
The factory operates for 1000 minutes/day
Daily operating time= factory operates 1000 minutes per day
Schedule output = 500 El
Hence, to calculate the required cycle time for the assembly line
Cycle time = daily operating time ÷ the output schedule.
1000 / 500 = 2 minutes