Respuesta :
Answer:
Underapplied
Explanation:
To determine, calculate the following;
Actual overhead = $1,170,000
Applied overhead = 150% * Direct labor cost
Applied overhead = 150% * $545,000
Applied overhead = $817,500
Note that the $817,500 overhead cost was not the actual cost reported in the T account, thus it was Underapplied since the actual amount ($1,170,000) of factory overhead incurred was greater than expected.
Answer:
Under applied overhead $ 352,500
Explanation:
The over or under applied overhead is the difference between applied(absorbed overhead) and actual overhead.
Applied overhead = OAR × actual labour cost
$
Applied overhead (150%×545,000) = 817,500
Actual overhead 1,1170,000
Under applied overhead 352,500
This implies that the amount charged to the Production(work in progress ) account for absorbed overhead is less than the actual overhead by $352,500