Respuesta :
Answer:
a. 22.30 machines required
b. 22.22mm
c. 11 machines
Explanation:
Please see attachments for guide



Complete Question
The complete question is shown on the first uploaded image
Answer:
The number of CNC machine required is [tex]N_{CNC} = 12 \ Machines[/tex]
Explanation:
From the question awe are told the
The machine availability is [tex]M_a =[/tex] 85%
The Rejection time is [tex]R_t =[/tex]4%
The lapping time is [tex]L =[/tex]20 minutes
The time to work between machines is [tex]T_b =[/tex][tex]30s[/tex] [tex]= \frac{30}{60} = 0.5minutes[/tex]
The loading and unloading time [tex]k= 90sec = \frac{90}{60} = 1.5 minutes[/tex]
For one the loading and unloading time would be
[tex]k_{one\ block} = L + T_b +k[/tex]
Substituting values
[tex]k_{one \ block} =20+ 0.5+1.5[/tex]
[tex]= 22 minutes[/tex]
for the 8 different sizes of the block the loading and unloading time would be
[tex]k_{8 \ different \ sizes } = 8*22[/tex]
[tex]= 176 \ minutes[/tex]
From the the target is given as
[tex]T = 120 \ sets /week[/tex]
The available time is given as
[tex]A = (5 \ day / week \ 8 \hr /day , 1 hr \ for \ lunch /break) M_a[/tex]
[tex]=( 5*8) -(5 \ hours \ of \ lunch \ break \ 1 \ hour \ per \ day) * 0.85[/tex]
[tex]= 29.95 hrs[/tex]
[tex]A = 29.95 *60[/tex]
[tex]= 1797 \ minutes[/tex]
The quantity of sets of block to be lapped by one machine per week would be
[tex]=\frac{A}{k_{8 \ different \ sizes } }[/tex]
[tex]= \frac{1797}{176} *(100- R_t)[/tex]%
[tex]= \frac{1796}{176} * 0.96[/tex]
[tex]=9.796[/tex] sets
Hence
The number of CNC lapping machine would be
[tex]N_{CNC} =\frac{120}{9.796}[/tex]
[tex]\approx 12 \ machines[/tex]

