the correct answer is Eliminate tasks on the critical path.
Explanation:
Critical path is the set of activities which are essential or "critical" for the success of the process. If we truly need to reduce the length of a project, we should find innovative ways to reduce the number of critical processes in the critical path.
The critical path is known to have a lot of chain of linked tasks that often affects the project finish date. One approach to reducing project length would be to Eliminate tasks on the critical path.
- The critical path often has series of tasks or sometimes a single task. This often controls the calculated start or finish date of the project.
An individual can be able to shorten the overall project timeline by putting together or compressing a task on the critical path.
Critical path gives room for teams to identify the most important tasks in a project.
Learn more from