Respuesta :
Answer: N = 96.04
Explanation:
To check if the engineer has met with all required, let us calculate the number of spot speed observations by considering the number of spot speed observations, the standard deviation corresponding to the required confidence level, and d the limit of acceptance error in the average speed estimate.
Please find the attached file for the solution
![Ver imagen temdan2001](https://us-static.z-dn.net/files/d85/24d80ae0888ae557e51624befa7dd547.jpg)
Answer:
No
Explanation:
confidence level 95%
Z= 1.96
margin of error (d) = 1
variance = 25
S.D = [tex]\sqrt{variance}[/tex] = [tex]\sqrt{25}[/tex] = 5
To check if the minimum size requirements are met we apply
N = [tex]\frac{Z*S.D}{d} = (\frac{1.96*5}{1} )[/tex] = 96.04
The engineer did not meet all the requirements of the study since the 130 spot sample collected has a minimum sample size of 97