Answer:
If batch size is more than 11,024 we will prefer B process otherwise we will prefer Process A.
Explanation:
Given,
Setup time of Process A = 40 minutes.
Setup time of Process B= 180 minutes.
The production time for the x batch size in the process A is given by Ta(x)=40+0.015×x
The production time for the x batch size in the process B is given by
Tb(x)=180+0.0023×x
Equating the both equations to the find the balancing point Ta(x) =Tb(x)
40+0.015×x = 180+0.0023×x
Rearranging the terms in the equations and bringing the similar terms on same side of the equation.
x×(0.015-0.0023) = 180-40
⇒0.0127×x = 140
x = 11,023.6
Round off x we get x= 11,024
Therefore if batch size is more than 11,024 we will prefer B process otherwise we will prefer Process A.