Project P requires an investment of 4000 at time 0. The investment pays 2000 at time 1 and 4000 at time 2. Project Q requires an investment of X at time 2. The investment pays 2000 at time 0 and 4000 at time 1. The net present values of the two projects are equal at an interest rate of 10%. Calculate X.