Answer:
TRUE
Explanation:
It is true that In a Program Evaluation Review Technique (PERT)/Critical Path Method (CPM) chart, each rectangular box, called a task box, has five sections that contain important information about a task.
By definition, The program evaluation review technique (PERT) and critical path method (CPM) are project management tools useful in planning, scheduling, and managing complex projects.
The key concept in CPM/PERT is that a small set of activities, which make up the longest path through the activity network, control the entire project.
The 5 sections that contain important information about a task are:
1. Task duration or time (T)
2. Earliest Start (ES)
3. Earliest Finish (EF)
4. Late Start (LS)
5. Late Finish (LF)