Answer:
The overhead cost using ABC is $9,097.41
Explanation:
Activity Cost Pool of products is as:
Setting up batches of ABC = Activity Rate × Total Activity
where
Activity Rate = $59.06 per batch
Total activity = 84 batches
So,
Setting up batches = $59.06 × 84
= $4,961.04
Processing customer orders of ABC = Activity Rate × Total Activity
where
Activity Rate = $72.66 per order
Total activity = 32 orders
So,
Processing customer orders = $72.66 × 32\
= $2,325.12
Assembling products of ABC = Activity Rate × Total Activity
where
Activity Rate = $3.75 per AH
Total activity = 483 AHs
So,
Assembling products = $3.75 × 483
= $1,811.25
Therefore, the overhead cost would be computed as:
Overhead cost = Assembling products of ABC + Processing customer orders of ABC + Setting up batches of ABC
Overhead cost = $1,811.25 + $2,325.12 + $4,961.04
Overhead cost = $9,097.41