Answer:
Material Equivalent Units= 29,700
Conversion Costs Equivalent Units= 27,780
Explanation:
Units % of Completion Equivalent Units
Mat. C.C Mat. C.C
Units started and completed 26,500, 100% 100% 26,500 26,500
Ending work in process 3,200 units 100% 40% 3200 1280
Total Equivalent Units 29,700 27,780
Pix uses the FIFO method to compute equivalent units. If unit materials cost is $6 and unit conversion cost is $11. The total costs to be assigned are $483,780,
Materials = $6* 29,700= $ 178,200
Conversion Costs = $ 11 * 27,780= $ 305,580
Total costs = $ 483,780