Explanation:
The computation of the overhead amount is shown below:
= (Milling department machine hours + cutting department machine hours) × overhead rate per machine hour
= (2,350 machine hours + 3,990 machine hours) × $7
= 6,340 machine hours × $7
= $44,380
So for assigning the overhead cost we have to credited the manufacturing overhead for $44,380