Answer:
The equivalent units of production for materials = 2,112 units
Explanation:
Equivalent units are notional whole units which represent incomplete work and are used to apportion costs between work in progress and completed units.
Equivalent units = Degree of work done(%) × units of inventory
So we can work out, the value of equivalent units as follows:
Items units Workings Equivalent units
Completed units 2,100 2,100 × 100% = 2,100
Closing WIP 120 120 × 10% = 12
Total equivalent unit for material 2,112
Total equivalent unit = 2,100 +12 =2,112 units
The equivalent units of production for materials = 2,112 units