Answer:
The Manufacturing cycle efficiency = 69 %
Step-by-step explanation:
The waiting time is = 72 minute
The manufacturing lead time is ( [tex]T_{lead}[/tex] )= 160 minutes
Total cycle time ( [tex]T_{c}[/tex] ) = 160 + 72 = 232 minutes
Manufacturing cycle efficiency = [tex]\frac{T_{lead} }{T_{c} }[/tex]
⇒ Manufacturing cycle efficiency = [tex]\frac{160}{232}[/tex]
⇒ Manufacturing cycle efficiency = 69 %
Therefore, the Manufacturing cycle efficiency = 69 %