Zenich Corp manufactures laptops. The waiting time is 72 minutes before the start of production and the manufacturing lead time is 160 minutes per laptop. What is its manufacturing cycle​ efficiency? (Round to the nearest whole​ percent.)

Respuesta :

Answer:

The Manufacturing cycle​ efficiency = 69 %

Step-by-step explanation:

The waiting time is  = 72 minute

The manufacturing lead time is ( [tex]T_{lead}[/tex] )= 160 minutes

Total cycle time ( [tex]T_{c}[/tex] ) = 160 + 72 = 232 minutes

Manufacturing cycle​ efficiency =  [tex]\frac{T_{lead} }{T_{c} }[/tex]

⇒ Manufacturing cycle​ efficiency = [tex]\frac{160}{232}[/tex]

⇒ Manufacturing cycle​ efficiency = 69 %

Therefore, the Manufacturing cycle​ efficiency = 69 %