Answer:
1. February – Budgeted direct labor hours = 378; Budgeted direct labor cost = $3,024.
2. March – Budgeted direct labor hours = 413; Budgeted direct labor cost = $3,304.
Explanation:
1. February direct labor budget:
a. Number of direct labor-hours budgeted for February = 0.07 * 5,400 = 378 labor hours
b. February budgeted direct labor cost = 378 * $8.00 = $3,024
2. March direct labor budget:
a. Number of direct labor-hours budgeted March = 0.07 * 5,900 = 413 labor hours
b. March budgeted direct labor cost = 413 * $8.00 = $3,304.00