Answer:
spending = $6,000
Scheduled variance= -$6,000
SPI = 0.964
CPI = 1.038
Explanation:
Define the values.
The project value (PV) = $168,000
The actual cost (AC) = $156,000
Estimated value (EV) = $162,000
FIND THE SPENDING:
The spendings are the cost value, which is calculated as
CV = EV - AC
CV = $162,000 - $156,000 = $6,000
FIND THE SCHEDULED VARIANCE:
The scheduled variance (SV) is calculated as
SV = EV - PV
SV = $162,000 - 168,000 = -$6,000
FIND THE SCHEDULED PERFORMANCE INDEX (SPI)
SPI = EV ÷ PV
SPI = $162,000 ÷ $168,000 = 0.964
FIND THE COST PERFORMANCE INDEX (CPI)
CPI = EV ÷ AC
CPI = $162,000 ÷ $156,000 = 1.038