Answer:
$7,695
Explanation:
The computation of the total cost is shown below:
Total cost = Direct material cost + total direct labor cost + total overhead cost
where,
Direct material cost = $2,103
Total direct labor cost = 35 direct labor hours × $17 = $595
And, the total overhead cost is
= 263 machine hours × $19
= $4,997
So, the total cost is
= $2,103 + $595 + $4,997
= $7,695