Answer:
Schedule Variance is - $223,500
Cost Variance = - $38,500
Explanation:
Difference between the two values are variance it could be positive and negative variance.
As per gicen data
Planned Value = PV = $735,000
Actual Cost = AC = $550,000
Completion ratio = Days spent / Total days = 65 / ( 65 + 5 ) = 0.93
Earned value = EV = Actual cost x completion ratio = $550,000 x 0.93 = $511,500
Schedule Variance (SV) = EV–PV = $511,500 - $735,000 = - $223,500
Cost Variance (CV) = EV–AC = $511,500 - 550,000 = - $38,500