Respuesta :
Answer:
(a) To maximize profit select the medium scale expansion profit.
(b) To minimize risk or uncertainty select the medium scale expansion profit.
Step-by-step explanation:
The data provided is:
Medium Scale Large Scale
Expansion Profit Expansion Profit
x f (x) y f (y)
Low 50 0.2 0 0.2
Demand Medium 150 0.5 100 0.5
High 200 0.3 300 0.3
(a)
The formula to compute the expected value of a probability distribution is:
[tex]E(U) = \sum u. f(u)[/tex]
Compute the expected value of medium scale expansion profit as follows:
[tex]E(X)=\sum x.f(x)=(50\times0.2)+(150\times0.5)+(200\times0.3)=145[/tex]
Compute the expected value of large scale expansion profit as follows:
[tex]E(Y)=\sum y.f(y)=(0\times0.2)+(100\times0.5)+(300\times0.3)=140[/tex]
To maximize the profit implies that we need to select the plan that will earn us a higher expected profit.
The expected profit earned from the medium scale expansion profit is $145,000.
This is more than the expected profit earned from the large scale expansion profit.
Thus, to maximize profit select the medium scale expansion profit.
(b)
The formula to compute the variance of a probability distribution is:
[tex]V(U) = \sum (u-E(u))^{2}. f(u)[/tex]
Compute the variance of medium scale expansion profit as follows:
[tex]V(X) = \sum (x-E(X))^{2}. f(x)\\=[(50-145)^{2}\times0.2]+[(150-145)^{2}\times0.5]+[(200-145)^{2}\times0.3]\\=2725[/tex]
Compute the variance of large scale expansion profit as follows:
[tex]V(Y) = \sum (y-E(Y))^{2}. f(y)\\=[(0-140)^{2}\times0.2]+[(100-140)^{2}\times0.5]+[(300-140)^{2}\times0.3]\\=12400[/tex]
To minimize the risk or uncertainty implies that the variance must be as small as possible.
The variance for medium scale expansion profit is less than the large scale expansion profit.
Thus, to minimize risk or uncertainty select the medium scale expansion profit.