Answer:
14.44 units per hour
Explanation:
Given
Factory produces = 130,000 televisions per quarter
Total production hours used by the factory per quarter = 9,000
Velocity in units per hour = No produced รท Time taken
Velocity in units per hour = 130,000 / 9,000
Velocity in units per hour = 14.44 units per hour