Answer:
Option (A) is correct.
Explanation:
Given that,
Formula for maintenance cost: Y = $5,300 + $0.60X
X is machine-hours
Planned machine time for August budget = 8,000 hours
Therefore,
Maintenance cost expected to be incurred during August:
= $5,300 + $0.60X
= $5,300 + ($0.60 × 8,000)
= $5,300 + $4,800
= $10,100
Therefore, the maintenance cost is $10,100.