The critical path and the minimum project time are (a) CEFH, 21 hours
Critical path
This is the longest path on the chart
Considering the options, we have:
[tex]CEFH =6 + 8 + 4 = 18[/tex]
[tex]BEFH =4 + 8 + 4 = 16[/tex]
[tex]ADFH =5 + 7 + 4 = 16[/tex]
In the above computation, 18 is greater than 16.
Hence, the critical path is CEFH
Minimum project time
This is the smallest time that the project can be completed.
On the chart, all path ends at 21 hours.
Hence, the minimum project time is 21 hours