The ____ provide(s) schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity.
A. Activity list
B. Milestones
C. Activity descriptions
D. Activity attributes