Respuesta :
Answer:
(D) $48 per machine hour
Explanation:
The predetermined overhead rate is given by total estimated overhead divided by the total estimated machine hours
Total estimated overhead = $7,584,000
Total estimated machine hours = 158,000 hours
Predetermined rate = $7,584,000 ÷ 158,000 hours = $48 per machine hour
Answer:
d. $ 48 per machine hour
Explanation:
To calculate the predetermined overhead rate based on machine hours, we have to divide the total forecasted overhead cost with the forecasted overhead machine hours.
The predetermined overhead rate based on machine hours is:
$ 7,584,000 / 158,000 = $ 48 per machine hour.