Answer:
The correct anwer is D.
Explanation:
Giving the following information:
Estimated direct labor hours 10,400
Estimated factory overhead costs $156,600
To calculate the estimated overhead rate, we need to use the following formula:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 156,600/10,400= $15.06 per direct labor hour.