Answer:
Most likely time, according to PERT (Program evaluation and review technique).
Step-by-step explanation:
PERT is "a statistical tool used in project management" (Program evaluation and review technique (2020), in Wikipedia), and it is commonly used with CPM (Critical Path Method) to manage projects.
Inside PERT, there are different defined times to accomplished an activity in a project, that is:
Considering the question, we have that the time when "the first module of the project could be completed":
As a result, the 20-day estimate is called the most likely time in the context of the PERT/CPM techniques.