Respuesta :

Answer:

The slack for any activity on the critical path will be zero.

Option: (B)

Explanation:

  • The critical path is characterized by complications of operations and intermingling of various factors.
  • These factors in the critical path are of prime importance and are usually paid great attention to in order to avoid operation failures.
  • Hence, the possibility of slack for any activity that is being conducted on the path that is critical for the operation is usually zero.