Answer:
total cost to be accounted = $294,000
Explanation:
Work in Process
Beginning value of WIP = $24,000
Ending value of WIP = $13,000
Cost added to production = $283,000
Cost to be accounted for = Beginning value of WIP + Cost added to production - Ending value of WIP
Cost to be accounted for = $24,000 + $283,000 - $13,000 = $294,000