You are the project manager of the BHY Project. Your project customer has demanded that the project becompleted by December 1. December 1 is an example of which one of the following?A. ConstraintB. AssumptionC. Project boundaryD. Product acceptance criteria

Respuesta :

Answer:

A. Constraint

Explanation:

A project constraint is a limit to a project. The three most common types of project constraints are:

  • Scope constraint - the project can be very ambitious and try to become a market leader, or it can be very niche and limited in scope.
  • Budget constraint - the project can have a very large budget, or it could be limited by very scarce economic resources.
  • Time constraint - the project might have to be completed in a long or in a short period of time.

In this case, as a project manager of BHY, your project has a time constraint: you must completed it by December 1, no matter what.