Answer:
The project should not be accepted.
Explanation:
By using the modified internal rate of return (MIRR) the project offers a discount rate of 10,29% to make the net present value equal to zero. This means that at a discount rate of 12.5% the net present value is negative, and the company would lose money. The company should look for another project with higher inflows for the same initial cost ($251.000)