An organization is conducting their first PI Planning session, and the new teams are asked to provide their capacity. Which three actions are part of the initial capacity planning process?

Respuesta :

Answer:

The three actions are:

Organisational readiness

Content readiness

Facility readiness

Explanation:

1. Organisational readiness - before planning, the event organisers must consider the following:

  • Is the scope of the planning process understood and do the organisers know which teams need to plan together?
  • Is there a reasonable agreement on priorities among the Business Owners
  • Is there dedicated developers and test resources and an identified Scrum Master and Product Owner for the team?

2. Content readiness - It is essential to make sure that there is a clear vision and context and that the right stakeholders participate. The PI planning must include:

  • A briefing that describes the current business context
  • Briefings that are done by Product Management
  • A presentation conducted by the CTO, Enterprise Architect or System Architect to communicate new enablers.

3. Facility readiness - an infrastructure that can accommodate a large number of attendees is important. The following needs to be take into consideration:

  • the space must be enough for the people that are attending
  • the tech support people need to be contacted with as early as possible and also reachable during setup and testing and also during the event
  • communication channels