Answer:
a. 17.6 days
b. 1.9 days
c. 0.8 days
Explanation:
The computation is shown below:
a. Wait time
= Delivery cycle time - average throughput time
= 25.2 days - 7.6 days
= 17.6 days
b. Process time
= Manufacturing cycle efficiency (MCE) × average throughput time
= 0.25 × 7.6 days
= 1.9 days
c. Inspection time
= Average throughput time - process time - average move time - average queue time
= 7.6 days - 1.9 days - 0.9 days - 4.0 days
= 0.8 days