Answer:
(1) 37,500 hours
(2) 7,500 kits
(3) 750 units
Explanation:
(1) Standard Hours allowed for 7500 rebuilt units:
= 7,500 × Direct labor hours
= 7,500 × 5 hours
= 37,500 hours
(2) Standard number of kits:
= 7,500 x 1 kits
= 7,500 kits
Standard number of cabinets:
= 7500 × 1 kits
= 7500 kits
(3) Number of units rebuilt:
= standard hours allowed for the units rebuilt ÷ Direct labor hours
= 3,750 ÷ 5
= 750 units