Answer: The correct answers are:
- profits.
- profits.
- costs.
- contract price.
- interest.
Explanation: In a construction contract, if the owner breaches before construction begins, the contractor can receive profits. If the owner breaches during construction, the contractor can recover profits plus costs incurred. If the owner breaches after construction is completed, the contractor can receive the contract price plus interest.