Answer:
b. Accept Project A and reject Project B.
Explanation:
To verify project viability at a required return rate of 16%, simply calculate the project's net present value at a rate of 16%. If the NPV is positive, then the project should be accepted, otherwise it should be rejected.
Project A:
[tex]NPV = -\$125,000 +\frac{\$46,000}{(1+0.16)} +\frac{\$79,000}{(1+0.16)^2} +\frac{\$51,000}{(1+0.16)^3}\\NPV =\$6,038.58[/tex]
Project A should be accepted.
Project B:
[tex]NPV = -\$135,000 +\frac{\$50,000}{(1+0.16)} +\frac{\$30,000}{(1+0.16)^2} +\frac{\$100,000}{(1+0.16)^3}\\NPV =-\$5,535.89[/tex]
Project B should be rejected.