Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 30 parts. A part requires 5 minutes in milling and 7 minutes in finishing. The move time between the two operations for a complete batch is 5 minutes.
Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 4 parts and the move time is eliminated.
Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place.
Traditional Philosophy Lean Manufacturing Philosophy
Value-added time 12min 12min
Non-value-added time min min
Total lead time 365min 48min
Value-added ratio (as a percent) % %