A tracking Gantt chart:
a. monitors costs and budget expenditures.
b. identifies key points in the project's progress.
c. identifies the stage of completion for each task.
d. identifies the performance to budget for the overall project by a certain date.

Respuesta :

Answer: The correct answer is "c. identifies the stage of completion for each task.".

Explanation: A tracking Gantt chart identifies the stage of completion for each task.

The Gantt chart is a graphic tool whose objective is to expose the expected dedication time for different tasks or activities over a given total time and thus identify the stage of completion of each task.