Answer:
Predetermined rate = Budgeted fixed manufacturing overhead
Budgeted direct labour hours
= $36,000
10,000 hours
= $3.60 per direct labour hour
Explanation:
Predetermined rate is the ratio of budgeted fixed manufacturing overhead to budgeted direct labour hours. Thus, the division of budgeted fixed manufacturing overhead by budgeted direct labour hours gives the predetermined rate.